Thursday, September 6, 2012

$5.56M BONNE TERRE BRIDGE

14 comments:

Anonymous said...

Yeah right! Every project is in the millions of dollars. Take care you all can't account for the money when your term is over.

Anonymous said...

@10:44AM U IN IT 2?

GO BACK AND MC YOUR MA.
DEAD BRAIN!!!!!

jeff daniel said...

a small bridge 5.56 million dollars aa this looks like reckless spending me

jeff daniel said...

what a rip off

Anonymous said...

Peep...the jobs need an independent cost review////they all look out of wack..

Anonymous said...

Hey Jeff I agree with you. The contracting company's is also suspicious. INTEGRATED Development organization.We are surely getting rip-off big time in this country by pip and his gang!

Anonymous said...

Pip, we need help in Cabiche Babonneau. The road is in a deplorable and impassable state. We are Labourites too and deserve some attention. Help us please! Babonneau youth are languishing without jobs, and little attention, if any, is given to us. Help us or kiss our votes good bye come next election.

Better Days Ahead said...

when will the gov decide to go ahead with the 4 lane highway...its long overdue.. fortunately i dont live in gros islet.. i mean its chaos to travel on a morning esp if minor accidents occur on their..in addition by widening the road to a 4 lane.. minimal tragic accidents will be curtailed..

gros islet has alot of potential but they need to widen that small road.. what about the choc bridge when will they tackle that one.. so far the bois dorange and this one next is teh choc bridge needs widening big time

Anonymous said...

I am of the viEw that we have unDerestimated global warming conditions by A large margin. At the current polar icecap melting rates the entire marina and its environs will be under water wheN rising sea levels are taken into Consideration. This bridge seems like a total waste after that fact is added to the equation.

Anonymous said...

JUST A MATTER OF TIME BEFORE THE BOBOL STARTED BUT PIP IF YOU THINK THE LAST BOBOL MONEY YOU LOSE TO YOUR INLAW YOU COME MAKE BACK CRAPO SMOKING YOUR PIPE

Anonymous said...

His summarized costs are as follows:

• General items -- $1, 216, 810.00
• Demolition and site clearance -- $99, 100.00
• Bridge works -- $1, 587, 845.00
• Road works -- $1, 074, 465.00
• Temporary bypass road -- $985, 750.00
• Contingency of 12% of the contract cost -- $595, 676.00

These are expenditure captions not a summary.
Hope the full expenditure will be available to the public --it's the people's money.

Anonymous said...

Interesting five months after a budget allocation of 13.37million for repair and maintainance of road bridges one bridge will cost 5.5m just under half of the total allocations. How many bridges are air marked for repairs and maintainance?

Anonymous said...

Pip we need a road in Cabiche, Babonneau.

Anonymous said...

A & M should have gotten that job, so there would have been no tender and budget breakdown.